Project Profile
FM Global
New headquarters for Fortune 500 insurance company

FM Global is the world’s leading insurer of industrial and commercial property risk. The company engaged Odeh Engineers as part of a design-build team in early 2008 to build a new 357,000 gsf office, data center, and parking garage to replace its existing nearby offices. Due to an expiring lease, FM Global required the team to complete the project on an extremely aggressive 18-month schedule.

By using BIM and 3D structural design tools, the Odeh team completed design of an early steel and foundation package in less than 60 days. This, in turn, enabled a nearly seamless process of shop drawing review, fabrication and erection was used to deliver the project on schedule and with minimal field changes.
Client
Vision 3 Architects

Location
Johnston, Rhode Island

Timing
Construction Completed September 2009
Design Highlights
  • Design included compliance with all FM Global Data Sheets and standards
  • Structural steel frame with composite slab on deck floor and roof structures. Odeh team used BIM to complete construction documents in 60 days.
  • Long span floors (52’) were designed for vibration control and to allow for a flexible and open plan layout by the architect
  • The data center was designed as a separate building with higher importance factors
  • Building information model was shared with the design-build contractor to perform detailed coordination modeling of all MEP systems
Construction Type
  • Steel
  • Masonry
Building Uses
  • Office